Coordination failure · United States
Grid interconnection queues hold 2,061 gigawatts — 75 percent of past requests were withdrawn
At the end of 2025, 2,061 gigawatts of generation and storage capacity were actively waiting for permission to connect to the electric grid in the United States. The queue shrank 10 percent during that year, but it shrank because projects gave up rather than because they were co…
- Resolution status
- not confirmed
- Checked
- 2026-08-07
- Evidence type
- SecondaryPress reports and institutional documents
- Outlet
- not recorded
- Authoring mode
- Derived from press reports
- Views
- 22
Note: the Berkeley Lab report that supplies the headline figures was not read directly — the PDF exceeds the fetch size limit and the numbers here come from two summaries of it.
What is happening?
At the end of 2025, 2,061 gigawatts of generation and storage capacity were actively waiting for permission to connect to the electric grid in the United States. The queue shrank 10 percent during that year, but it shrank because projects gave up rather than because they were connected. Of the capacity that entered a queue between 2000 and 2020, 13 percent had reached commercial operation by the end of 2025 and 75 percent had been withdrawn.
The wait is measured in years. In 2025 the median time from submitting a request to signing an interconnection agreement was well over three years, and the median time to reach commercial operation exceeded five years. The composition of the line also flipped in a single year: natural gas capacity in the queue rose 86 percent to 253 gigawatts, while solar fell 19 percent to 773 gigawatts, storage fell 16 percent to 749 gigawatts and wind fell 19 percent to 220 gigawatts.
By the middle of 2026 the active queue was down to 1,919 gigawatts. In that half year 245 gigawatts across 1,319 projects were withdrawn and 224 gigawatts of new applications came in.
Whose problem is this?
| Role | Who |
|---|---|
| Affected | Developers of grid-scale generation and storage · electricity customers in regions where new supply is delayed · large new loads such as data centers |
| Raised by | Berkeley Lab (annual Queued Up series) · FERC · ISO and RTO stakeholder processes · trade and advocacy organizations |
| Decides | FERC (the interconnection rule) · each of more than 50 transmission providers (the study queue itself) · state siting authorities (the transmission lines the studies call for) |
| Bears the cost | The interconnection customer (fees, deposits, network upgrades) · ratepayers (socialized upgrade costs and capacity prices) · the load that cannot be served |
The party that sets the deadline is not the party that runs the clock. FERC wrote a single national rule; more than 50 separate transmission providers each file their own compliance plan and each operate their own queue, and none of them can build the transmission a study calls for without a state siting decision.
Where does this problem end?
| Axis | This is the problem | This is not the problem |
|---|---|---|
| What | The wait and the withdrawal rate in the transmission interconnection study process | Distribution-level hookups for rooftop solar run through a different queue |
| Building the transmission lines themselves is adjacent, not identical | ||
| Who | Developers of grid-scale generation and storage, and the transmission providers that study them | Retail customers are affected downstream but are not in the queue |
| Where | The United States — 7 ISO and RTO regions plus about 50 non-ISO balancing areas, together about 98 percent of installed capacity | Interconnection regimes outside the United States are out of scope |
| When | Annual figures as of end of 2025; the newest figures as of mid-2026 | Requests submitted before 2000 are outside the cohort statistics used here |
| Scale | 2,061 GW active at the end of 2025 | How much of that would have been built under a faster process is not confirmed |
The boundary matters here because this is not a permitting problem and not a supply chain problem. It is the step where a project asks the grid operator what connecting would cost, and then waits for the answer.
What is the state now, and what should it be?
Now
| Indicator | Value | As of |
|---|---|---|
| Active capacity in interconnection queues | 2,061 GW | end of 2025 |
| Change from the prior year | down 10 percent | 2025 |
| Solar · storage · wind · gas | 773 · 749 · 220 · 253 GW | end of 2025 |
| Median request to signed interconnection agreement | well over 3 years | 2025 |
| Median request to commercial operation | over 5 years | 2025 |
| Share of 2000-2020 cohort capacity now operating | 13 percent | end of 2025 |
| Share of the same cohort withdrawn | 75 percent | end of 2025 |
| Capacity holding a drafted or executed agreement | 536 GW · 26 percent of the active queue | end of 2025 |
| Two largest regional queues | non-ISO West 567 GW · one single-state ISO 408 GW | end of 2025 |
| Active capacity at the half year | 1,919 GW | 2026-06-30 |
| Median to commercial operation, projects completing in H1 2026 | 4.8 years | H1 2026 |
Should be
FERC Order No. 2023 gives a transmission provider 150 calendar days to complete an initial cluster study, and a late study now carries a penalty of USD 1,000 per business day for a cluster study and USD 2,500 per business day for a facilities study. That is the only binding federal clock in the chain, and it covers one step of the process rather than the whole path. One large multi-state RTO tells applicants under its reformed process to expect one to two years for a generation interconnection agreement.
How big is it?
What is measured is the capacity. The line held 2,061 GW at the end of 2025 and 1,919 GW at the end of June 2026, and in the first half of 2026 more capacity left than arrived. One monetized estimate exists for one region: an advocacy analysis argued that connecting 15 percent of the capacity proposed in the queue of one large multi-state RTO would have supplied more than the roughly 10 GW of accredited capacity needed to return the 2025 and 2026 auction to historical cost norms, worth as much as USD 7 billion in that single auction. The method behind that figure was not verified.
Fills with researchthe affected population was not researched. The queue is counted in gigawatts and in projects, and no source we opened converts a gigawatt-year of interconnection delay into a number of people who paid more for electricity or went without service. The affected population is therefore left `not-derivable`. Details in `population/us-grid-interconnection-queue.json`.
Under what conditions does it arise?
Four conditions hold this state in place, and no single party controls any of them.
1. The queue is a shared line. What one project is told it must pay depends on which other projects sit ahead of it, so every departure forces a restudy and moves the numbers for everyone behind. The withdrawal rate and the study delay are the same fact seen twice. 2. Entry was cheap relative to the option it bought. A request costs far less than the project it reserves a place for, so filing many requests and keeping the best has been rational for each applicant and has clogged the queue in aggregate. Order No. 2023 raised the price of a place in line — a USD 5,000 application fee, a study deposit between USD 55,000 and USD 250,000, and control of 90 percent of the site acreage at submission. 3. One author, more than fifty implementers. FERC wrote the rule, but each transmission provider files its own compliance plan on its own schedule. In July 2025 FERC accepted the compliance plan of one large multi-state RTO only in part and gave it 60 days to propose further changes, two years after the rule issued. 4. Finishing the study is not the same as finishing. More than 40 percent of capacity is still withdrawn after an interconnection agreement has been signed, so speeding the study up does not by itself deliver a power plant.
What has been tried?
| Attempt | By whom | What was done | When |
|---|---|---|---|
| Order No. 2023 | FERC | Replaced serial first-come-first-served study with a first-ready-first-served cluster study; set a 150-day cluster study deadline; added per-day penalties for late studies; raised deposits and required 90 percent site control at submission | issued 2023-07-28 |
| Compliance deadline extension | FERC | Moved the compliance filing deadline for most transmission providers from 2023-12-05 to 2024-04-03 | 2023-10 |
| Compliance enforcement | FERC | Accepted the compliance filing of one large multi-state RTO only in part and directed a further compliance filing within 60 days | 2025-07-24 |
| Transition cycles to drain the old backlog | One large multi-state RTO | Closed the queue in 2022 and ran two transition cycles. Cycle 1 ended with draft agreements for 128 generation projects totaling about 17.4 GW; about 46 GW remained for Cycle 2, to be processed by end of 2026 | 2023-2026 |
| Reopening under the reformed process | The same RTO | Reopened with an application deadline of 2026-04-27 and received more than 800 projects totaling 220 GW, of which 106 GW is gas and 15 GW is solar | 2026-04 |
| Readiness screen at a study milestone | Another RTO | In a 2024 cluster study, 126 projects totaling 28.5 GW dropped out at the phase-one decision point once they saw their study results | 2026 |
What was found?
| Finding | Observed value | Evidence grade |
|---|---|---|
| The queue is shrinking, and it shrinks by withdrawal | 2,290 GW end-2024 → 2,061 GW end-2025 → 1,919 GW mid-2026; H1 2026 saw 245 GW withdrawn against 224 GW of new applications | high |
| Most capacity that enters never connects | 13 percent of 2000-2020 cohort capacity online by end of 2025; 75 percent withdrawn | high |
| Withdrawal continues after the paperwork is done | more than 40 percent withdrawal even after an interconnection agreement is signed | medium |
| The wait grew for fifteen years and has only just turned | typical duration 22 months in 2008 · 36 months in 2015 · 55 months in 2024; median to operation over 5 years in 2025 and 4.8 years in H1 2026 | medium |
| Projects give up sooner than they used to | median time in queue before withdrawal 40 months in 2024 · 35 months in 2025 · 21 months in H1 2026 | medium |
| The mix in the queue flipped toward gas | Berkeley Lab — gas 253 GW at end-2025, up 86 percent in a year, and solar down 19 percent to 773 GW. The independent tracker counts a smaller base of 247 GW at end-2025 and 305 GW by mid-2026, with offshore wind down 58 percent to 6.9 GW | high |
| Agreements are being executed at record volume | 536 GW held a drafted or executed agreement at end-2025, 26 percent of the active queue; two large ISOs each executed more than 30 GW in 2025 | high |
| An agreement is not a power plant | One large multi-state RTO connected 2.1 GW in 2025 while holding about 46 GW of signed agreements as of June 2025 | medium |
| Reform has not yet shortened one large region | in one large multi-state RTO the average timeline from application to commercial operation rose from under 2 years in 2008 to over 8 years in 2025 | low |
| One region reports a very low completion rate | in one ISO about 9 percent of submissions are placed in service; the queue grew from 176 projects in 2018 to 350 in 2025, and only 5 battery storage projects totaling 100 MW have passed through it | low |
Why is it still unsolved?
Coordination failure — the wait is produced by how four sets of parties interact, and none of them can shorten it alone.
The queue is a shared resource whose answers are interdependent. A cluster study prices the network upgrades a group of projects would need together, so the number any one applicant receives depends on who else is in the group. When an applicant leaves, the study is redone and every remaining number moves. That makes speculative entry cheap for the individual and expensive for everyone else, and it makes late withdrawal the most damaging thing a participant can do. Order No. 2023 attacked exactly this by raising the cost of entry and by penalizing the study side for lateness, and the entry discipline has visibly worked — the median project now abandons the queue after 21 months rather than 40.
But the rule has one author and more than fifty implementers, and the pieces do not move together. Each transmission provider files its own compliance plan on its own schedule; two years after the rule issued, FERC accepted the compliance plan of one large multi-state RTO only in part on 2025-07-24 and directed a further filing within 60 days. Meanwhile the transmission a study calls for is sited by states, not by FERC and not by the grid operator, so the operator can complete a study on time and still be unable to deliver the connection.
The measured improvement is therefore ambiguous, and that ambiguity is itself part of why the problem persists. The queue got shorter mainly because projects left it. Withdrawals exceeded new applications in the first half of 2026. A shorter line and a faster median are exactly what a healthy process would produce, and they are also exactly what a process that discourages everyone from entering would produce.
What observation would mean it is solved?
Candidates — (a) the active queue falls toward the volume actually being connected each year (b) the median time from request to commercial operation falls below three years (c) the share of entering capacity that eventually operates rises well above the historical 13 percent.
(a) alone is satisfied by mass abandonment. The queue fell 10 percent in 2025 and another 3.5 percent in the first half of 2026, in a period when withdrawals of 245 GW outran new applications of 224 GW.
(b) alone is satisfied by survivorship. If readiness screens push out everything that would have been slow, the median falls without anyone being connected faster. The drop from 5.5 to 4.8 years is not separated from that effect in anything we read.
(c) alone can be met by admitting less. A queue that only lets in pre-approved projects would post a high completion rate and say nothing about how much generation the country actually added.
Read all three against the capacity energized per year. One large multi-state RTO connected 2.1 GW in 2025 while holding roughly 46 GW of signed agreements.
What is it connected to?
Fills with researchtransmission expansion and state siting · data center load growth · capacity market prices · equipment supply chains for transformers and turbines. Relation type and evidence grade were not confirmed in this round.
What these sources do not say
- How much of the 75 percent withdrawal the queue itself caused. Financing, offtake contracts, siting and equipment supply also kill projects, and none of the sources read here separates those causes from study delay. Without that split the queue cannot be assigned a share of the loss.
- What network upgrade costs the studies actually assigned. The 2024 cluster study recorded above shows 28.5 GW leaving immediately after the study results were issued, which implies the cost number is decisive, but the distribution of those numbers is not published in anything we opened.
- Whether the late-study penalties have ever been assessed. Order No. 2023 sets a per-day amount but we found no count of penalties actually billed or paid, and no transmission provider named as having paid one.
- The distribution behind the medians. A median of 4.8 years says nothing about the tail, and regional queues differ by a factor of more than two in volume, so a national median may describe no region.
- Whether the swing to gas is new demand or reshuffling. Gas rose 86 percent in a year when every other resource fell, and no source distinguishes genuinely new gas projects from capacity that displaced other requests in the same interconnection position.
- What became of the capacity that left. No source tracks whether a withdrawn project re-entered a different queue, so the withdrawal totals may count the same megawatts more than once.
See the evidence
| Item | Source | Confirmation |
|---|---|---|
| 2,061 GW active end-2025 · down 10 percent · solar 773 · storage 749 · wind 220 · gas 253 GW · non-ISO West 567 · one single-state ISO 408 · 13 percent built and 75 percent withdrawn for the 2000-2020 cohort · over 40 percent withdrawal after an agreement · median over 3 years to agreement and over 5 years to operation · 536 GW under agreement, 26 percent of the queue · two large ISOs over 30 GW each | American Public Power Association, 2026-07-01, reporting Berkeley Lab Queued Up 2026 Edition | 2026-08-07 |
| Publication date 2026-06-30, authorship, and coverage of more than 50 transmission grid operators representing about 98 percent of installed US generating capacity | OSTI.GOV record 3376147 — Researcher A, Researcher B, Researcher C et al., Lawrence Berkeley National Laboratory | 2026-08-07 |
| Full text and figures of Queued Up 2026 Edition | Lawrence Berkeley National Laboratory, 2026-06 | URL not confirmed: the report PDF exceeds the fetch size limit, and the emp.lbl.gov landing pages return 403 |
| 2,290 GW at end-2024 · typical duration 55 months in 2024, 36 months in 2015, 22 months in 2008 · 19 percent of projects and 13 percent of capacity operating by end-2024 · 90 percent site control requirement | loopback.systems summary of Berkeley Lab Queued Up 2025 Edition, 2026-01-23 | 2026-08-07 |
| H1 2026 queue 1,919 GW, down 3.5 percent · 245 GW withdrawn across 1,319 projects · 224 GW of new applications · gas to 305 GW · solar down 4.7 percent to 682 GW · offshore wind down 58 percent to 6.9 GW · median 4.8 years to operation versus 5.5 years in 2025 · median withdrawal at 21 months versus 35 and 40 · a 2024 cluster study in one RTO loses 126 projects and 28.5 GW | interconnection.fyi newsletter, 2026-07-14 | 2026-08-07 |
| 2024 withdrawals of 296 GW, more than double 2023 · withdrawing projects had typically sat 4 to 5 years · median over 5.4 years before withdrawal in one large ISO | interconnection.fyi newsletter, 2025-06-02 | 2026-08-07 |
| Order No. 2023 issued 2023-07-28 · 150-day cluster study · penalties of USD 1,000 to USD 2,500 per business day · USD 5,000 application fee · deposit USD 55,000 to USD 250,000 · 90 percent site control · compliance deadline moved from 2023-12-05 to 2024-04-03 · over 2,000 GW waiting at end-2022 | K&L Gates client alert, 2023-09, updated after the 2023-10-25 extension order | 2026-08-07 |
| One large multi-state RTO reopened its queue at 220 GW across more than 800 projects — gas 106 GW, storage 67 GW, nuclear 18 GW, solar 15 GW, hybrid 9 GW, wind 5 GW · queue effectively closed since 2022 · reviews expected in one to two years | Utility Dive, 2026-04-29 | 2026-08-07 |
| Cycle 1 draft agreements in one large multi-state RTO for 128 generation projects totaling about 17.4 GW · about 46 GW remaining for Cycle 2 by end of 2026 · application deadline 2026-04-27 · 2.1 GW connected in 2025 · about 46 GW of signed agreements as of June 2025 | PJM Inside Lines, 2025-09-22 | 2026-08-07 |
| Cycle 1 decision point on 2024-06-20 in one large multi-state RTO — 310 projects entered, 96 withdrawn by sponsors, 10 discontinued for unmet readiness · 204 projects and 30,513 MW cleared to phase two across 12 states | PJM Inside Lines, 2024-08-06 | 2026-08-07 |
| Connecting 15 percent of the capacity proposed in the queue of one large multi-state RTO would supply the roughly 10 GW of accredited capacity needed to return the 2025 and 2026 auction to historical cost norms, worth up to USD 7 billion · 174 GW voluntarily withdrawn from that queue since 2022 | Advanced Energy United, 2026-02-04 | 2026-08-07 |
| In one large multi-state RTO the average timeline from interconnection application to commercial operation rose from under 2 years in 2008 to over 8 years in 2025 | RMI, 2025-11-04 | 2026-08-07 |
| In one ISO about 9 percent of submissions are placed in service · queue grew from 176 projects in 2018 to 350 in 2025 · only 5 battery storage projects totaling 100 MW have passed through the queue | Modo Energy, 2025-10-30 | 2026-08-07 |
| FERC acted on the Order No. 2023 compliance filing of one large multi-state RTO on 2025-07-24, accepting it in part and giving that RTO 60 days to propose further changes | Utility Dive, 2025-07-25 | 2026-08-07 |
The Berkeley Lab report itself was not read directly — the PDF exceeds the fetch size limit and the emp.lbl.gov landing pages return 403 — so the end-of-2025 figures come from two independent summaries of it, and the OSTI record was opened to confirm the publication date, the authorship and the coverage claim. Two numbers cross-check cleanly: the 2,061 GW reported for end-2025 as a 10 percent decline implies about 2,290 GW for end-2024, which is exactly the figure the summary of the prior edition gives.
Two discrepancies remain open. The 2024 withdrawal total is reported as more than 700 GW in the summary of the Berkeley Lab edition and as 296 GW by the independent tracker, a gap we could not resolve because the counting bases are not stated side by side. And the tracker puts the queue at 1,919 GW in mid-2026 after a 3.5 percent decline from 1 January, which implies about 1,989 GW at the start of 2026 rather than the 2,061 GW Berkeley Lab reports for end-2025; the two datasets clean and de-duplicate the same operator filings differently. The same gap shows in the gas total, which Berkeley Lab puts at 253 GW for end-2025 and the tracker at 247 GW, so the tracker rise to 305 GW by mid-2026 is measured against the smaller base. Figures attributed to a nonprofit research institute, to a commercial data provider and to an industry advocacy group are graded low because each publishes its own analysis and none of the underlying methods was verified; the third of those is additionally writing about a market it participates in. This is a Path A output, so observation_refs is empty and provenance_mode: press-derived.
This table holds 14 evidence rows, 13 of which carry a source you can open · 10 distinct sources. How this table is made
People affected
Estimated range Not derivable
The reason and what is missing are listed under “What is missing” below
What is missing 3
Grouped by how it gets filled, not by block number — that axis is the only one that tells a reader what can be done next.
- SectionHow big is it?
the affected population was not researched. The queue is counted in gigawatts and in projects, and no source we opened converts a gigawatt-year of interconnection delay into a number of people who paid more for electricity or went without service. The affected population is therefore left `not-derivable`. Details in `population/us-grid-interconnection-queue.json`.
Fills with research - SectionWhat is it connected to?
transmission expansion and state siting · data center load growth · capacity market prices · equipment supply chains for transformers and turbines. Relation type and evidence grade were not confirmed in this round.
Fills with research
- Derived valueThe affected population could not be derived
The queue is measured in gigawatts and in project counts, never in people. No source opened in this round converts a gigawatt-year of interconnection delay into a count of electricity customers who paid more or lost service. The counterfactual is also unestablished: of the capacity that entered a queue between 2000 and 2020, 75 percent had been withdrawn by the end of 2025, and no source separates withdrawals caused by study delay from withdrawals caused by financing, offtake, siting or equipment supply. Without that split, the number of people harmed by the queue cannot be distinguished from the number harmed by everything else that kills a power plant.
Retail electricity customer counts for the regions where the backlog actually binds on new supply, and a published attribution of price or reliability outcomes to interconnection delay rather than to the other causes of project failure. The only monetized estimate found covers a single capacity auction in one RTO, is worth as much as USD 7 billion by that account, and comes from an advocacy organization whose method was not verified.
Needs a new measurement
Voting and commenting require you to be signed in. Sign in from the account page
Comments
The comment was empty, so nothing was posted.
The comment exceeded the limit, so nothing was posted. We do not truncate and save.
You just posted a comment. Please try again in a moment.
The target comment could not be found, so nothing was posted.
You must be signed in to comment.
You have already reported this comment. Each person counts once — to withdraw it, use Cancel report under Reports you filed on the notifications page.
This report has already been reviewed. A judged report cannot be filed again or withdrawn.
No reason was chosen, or Other was picked without a note, so the report was not filed.
You cannot report your own comment or your own profile. Use Delete to take down your own comment.
Report received. Once 3 different people report it, the comment is hidden until review finishes — the outcome appears on your notifications page.
Voting and commenting require you to be signed in. Sign in from the account page
No comments yet.