All problems

Coordination failure · United States

42.45 billion dollars for broadband, appropriated in 2021 — no deployment project funded through August 2025

In late 2021 Congress appropriated 42.45 billion dollars for the Broadband Equity, Access, and Deployment program, the largest federal investment in broadband infrastructure to that date. NTIA notified the 56 states and territories of their allocations on 2023-06-30 and stated o…

Resolution status
not confirmed
Checked
2026-08-07
Evidence type
SecondaryPress reports and institutional documents
Outlet
not recorded
Authoring mode
Derived from press reports
Views
21
Note: the figures below are out of date. Nothing opened in this round reports how many locations had working service as of 2026-08.

What is happening?

In late 2021 Congress appropriated 42.45 billion dollars for the Broadband Equity, Access, and Deployment program, the largest federal investment in broadband infrastructure to that date. NTIA notified the 56 states and territories of their allocations on 2023-06-30 and stated on 2024-12-23 that the full 42.45 billion dollars had been obligated. As of August 2025, no eligible broadband deployment project had been funded from the BEAD money allocated to any state.

On 2025-06-06 NTIA issued a Restructuring Policy Notice that rescinded every final proposal approval already granted, removed seven non-statutory requirements including the low-cost service option, eliminated the fiber preference, and required all 56 to run a fresh subgrantee selection round. Bids came in far below the allocations. By 2026-02-09, 50 of the 56 final proposals had been approved and NTIA put the unspent remainder at about 21 billion dollars — roughly half the appropriation.

Whose problem is this?

RoleWho
AffectedHouseholds and businesses at the 3,379,711 locations reported without 100/20 Mbps service as of 2026-02
Raised byMembers of Congress · the Government Accountability Office · state broadband offices · a technology policy research institute · trade press
DecidesCongress (appropriation and statute) · NTIA (program rules, and approval of every initial and final proposal) · the 56 state broadband offices (subgrantee selection) · subgrantees (build schedule)
Bears the costThe unserved household, which keeps waiting · state broadband offices, which redid completed work · bidders, which prepared a second round of bids

The layer that resets the schedule and the layer that waits for a connection never deal with each other. NTIA approves states, states select subgrantees, and subgrantees connect households — a household has no counterparty at the level where the calendar is actually set.

Where does this problem end?

AxisThis is the problemThis is not the problem
WhatThe elapsed time between the 2021 appropriation and a working connectionWhether 42.45 billion dollars was the right amount is a separate question
Whether fiber or satellite is the better technology is a design dispute inside this program, not the definition of this problem
WhoHouseholds and businesses at locations without 100/20 Mbps serviceHouseholds that have service but find it expensive fall under affordability, which the 2025-06-06 notice removed from the program
WhereThe 56 states and territories holding BEAD allocationsOther federal broadband programs are out of scope
WhenFrom the 2021 appropriation through 2026-08Federal broadband subsidy before 2021 is out of scope
Scale42.45 billion dollars · 3,379,711 locations without service · about 21 billion dollars still unspentVariation between states was not researched

The boundary matters here because the money was never the binding constraint. It was appropriated in full, obligated in full, and then sat.

What is the state now, and what should it be?

Now

IndicatorValueAs of
Appropriated42.45 billion dollars2021
Reserved for administration and oversightup to 2 percent, or 849 million dollars2021
Obligated to states42.45 billion dollars, in full2024-12-23
Deployment projects funded from allocated BEAD moneynone2025-08
Final proposals approved by NTIA26 of 562025-12-02
Final proposals approved by NTIA50 of 562026-02-09
Underspend after the rebidabout 21 billion dollars2026-02-09
Locations without 100/20 Mbps service3,379,7112026-02-09
Locations funded by approved final proposals2,278,3552026-02-09
Locations left unfunded after BEAD1,101,3562026-02-09
Deployment cost per location in the rebid2,080 dollars in Maine to 13,420 dollars in Hawaii2025-09

Should be

Needs a new measurementno national completion date and no numeric coverage target appears in any source opened for this dossier. The only dated obligation confirmed is per subgrantee and statutory: a subgrantee must deploy the network and begin providing service to customers no later than four years after receiving the subgrant, and the state may extend that deadline under certain circumstances. That clock starts at the subgrant, which is the very step the program spent four years reaching.

How big is it?

The affected population is counted in broadband serviceable locations, not in persons. An analysis of the approved final proposals dated 2026-02-09 counted 3,379,711 locations in the United States without 100/20 Mbps service, of which 2,278,355 are funded by BEAD and 1,101,356 are funded by nothing at all.

The lower bound used here is 2,278,355 — locations that BEAD has now promised on paper and has not yet connected. The upper bound is 3,379,711 — every location still without service, funded or not. The unit is broadband serviceable locations rather than persons, so the number of people affected is larger than either bound. No household size figure was confirmed in this round, so that conversion was not attempted.

The same analysis reports that 33.7 percent of BEAD locations already have terrestrial service at 100/20 Mbps. The list of BEAD eligible locations and the list of locations actually without service are therefore not the same set, and the gap runs in both directions.

Under what conditions does it arise?

Three conditions hold this state in place, and a shortage of money is not one of them.

1. The approval chain has four layers. Congress appropriates, NTIA writes the rules and approves each state twice, the state selects subgrantees, and the subgrantee builds. A requirement added at any layer resets the work of every layer below it. The 2025-06-06 notice did exactly that — it rescinded final proposal approvals that three states had already obtained by 2025-01-16. 2. Nothing in the program measures elapsed time. The reported indicators are proposals approved, dollars obligated and dollars saved. None of them is a date by which a household is connected, and the only statutory clock starts at the subgrant rather than at the appropriation. 3. Delay produces no visible failure. An unserved household stays unserved, which looks the same as it did before the program existed. There is no interruption, no closure and no queue anyone can see, so a year of delay never registers as an event.

Each layer of approval can be reopened by the layer above it, and reopening resets the schedule of every layer below.

What has been tried?

AttemptBy whomWhat was doneWhen
Notice of funding opportunityNTIAPublished the program rules within 180 days of enactment2022-05-13
Planning fundsNTIA and the 56Up to 5 million dollars for each state and for the District of Columbia and Puerto Rico, and up to 1.25 million dollars for each of the four other territories, to stand up a broadband office2022-08 to 2023-06
Allocation by mapNTIA with FCC dataAllocations set from the first National Broadband Map, which carried availability data as of 2022-12-31. Range ran from 27.1 million dollars for the U.S. Virgin Islands to 3.3 billion dollars for Texas2023-06-30
Initial proposalsThe 56 and NTIAAmong the first approved on 2024-04-25 were Kansas, Nevada and West Virginia; all 56 approved by 2024-11-192024
Full obligationNTIAStated that all 42.45 billion dollars had been obligated to states2024-12-23
Program reviewDepartment of CommerceAnnounced a review to remove requirements, go technology neutral and address delay2025-03-05
Restructuring Policy NoticeNTIARescinded prior final proposal approvals, dropped the fiber preference and seven non-statutory requirements, gave 90 days to resubmit2025-06-06
Benefit of the Bargain RoundThe 56A fresh subgrantee selection round open to all qualifying technologies, deadline 2025-09-042025-06 to 2025-09
Final proposal approvalsNTIA26 of 56 approved by 2025-12-02, 50 of 56 by 2026-02-092025-11 to 2026-02
Listening session on the underspendNTIAPublic session on how the roughly 21 billion dollars may be used, with more than 1,000 unique participants2026-02-11

What was found?

FindingObserved valueEvidence grade
The appropriation was obligated in full long before any construction42.45 billion dollars obligated 2024-12-23; no deployment project funded as of 2025-08high — Congressional Research Service
A mid-flight rule change voided completed approvalsFinal proposals of Louisiana, Delaware and Nevada approved by 2025-01-16, then rescinded 2025-06-06high — Congressional Research Service
Rebidding cut the deployment cost sharplyLouisiana went from a 1.36 billion dollar allocation to a 498 million dollar deployment budget for roughly 124,000 locations; Delaware went from just over 100 million dollars to 13.4 million dollars for roughly 4,700 locationsmedium — legal trade analysis
The national underspend is large and stable across reportsAbout 21 billion dollars, reported on 2025-12-02 and again on 2026-02-09medium — two independent trade reports
The technology mix moved away from fiberAbout 66 percent of BEAD eligible locations to fiber, 21 percent to low earth orbit satellite, 11 percent to fixed wireless, read from draft plansmedium — trade press reading draft plans
Location counts moved in both directions during the rebidOhio rose 13 percent from its draft result; Indiana fell 7 percentmedium — trade press
The restructuring is legally contestedGAO opinion of 2025-12-16 held the 2025-06-06 notice to be a rule subject to the Congressional Review Actmedium — legal trade analysis and general press
A gap remains after BEAD1,101,356 locations without 100/20 Mbps service are covered by no approved final proposalmedium — independent analysis of final proposal data
How much has actually been builtnot confirmed in this round

Why is it still unsolved?

Coordination failure — the money, the rules, the selection and the shovel sit in four different places, and none of them is accountable for the time between them.

Congress put 42.45 billion dollars into a structure where NTIA must approve each of the 56 twice, each of the 56 must run its own competitive subgrant process, and each subgrantee then has a statutory four years of its own. Every one of those steps has an owner and a rule. No single actor in this chain owns the elapsed time between the appropriation and the first customer connected.

The 2025-06-06 notice shows what that costs. Three states had already cleared the last statutory step and were ready to sign agreements with the providers they had selected. The notice rescinded those approvals and sent all 56 back through subgrantee selection. The rebid was not pointless — bids came in roughly 21 billion dollars below the allocations, and Nevada reportedly covered every eligible location at lower cost — but the same change reset the calendar for every state, including the three that were finished.

The dispute over whether that change was lawful adds a layer rather than resolving one. On 2025-12-16 the Government Accountability Office issued an opinion that the notice was a rule subject to the Congressional Review Act, and reporting on 2026-01-05 described the finding as a violation of that act. That question sits above NTIA and below Congress, in the one place where no schedule exists at all.

What observation would mean it is solved?

Three candidates, and the trap in each.

a. The count of locations connected by BEAD funded networks rises toward the 2,278,355 that approved final proposals cover. The trap is that this is the paper target rather than the need — 1,101,356 locations without service are outside it from the start.

b. The count of locations in the United States without 100/20 Mbps service falls from 3,379,711 toward zero. The trap is attribution — other federal programs and private builds move the same number, and the BEAD share cannot be read off it.

c. All 56 sign award agreements and construction begins everywhere. The trap is that this is what the program has been measuring all along. Initial proposals and obligations each reached completion during 2024, and as of August 2025 no deployment project had been funded.

None of the three is sufficient alone because the program reports progress in the units of its own process. A completion measure has to be dated at the household, not at the filing.

What is it connected to?

Fills with researchplausible links run to the high cost programs of the Universal Service Fund, to the end of the Affordable Connectivity Program, to rural depopulation, and to the federal permitting timeline that the 2025-06-06 notice also addressed. Relation type and evidence grade were not researched in this round.

What these sources do not say

  • How much has actually been built. No source opened here reports a national count of locations connected by a BEAD funded network as of 2026-08. Reported milestones stop at proposal approval and award signature, which are filings rather than connections.
  • What the roughly 21 billion dollars will be spent on. NTIA held a listening session on 2026-02-11; the sources here record no published rule for non-deployment use afterwards.
  • Whether the rebid produced savings or scope reduction. Ohio saw its approved location count rise 13 percent from its draft and Indiana saw its fall 7 percent, and no source opened here reconciles the national location count before and after the 2025-06-06 notice.
  • What the technology shift means at the other end. About 21 percent of BEAD eligible locations are slated for low earth orbit satellite in the draft plans, and none of these sources reports a performance floor, a price commitment or a capacity ceiling for those locations.
  • Whether the Congressional Review Act finding changed anything in practice. The legal implication was reported: the restructuring cannot take effect until Congress is notified and given time to review. None of the sources here reports whether that notice was ever submitted, whether Congress acted on it, or whether any approval already granted was reopened because of it.
  • The distribution of the delay. Only national totals are reported. No source opened here breaks elapsed time down by state, so whether some states are years ahead of others is unknown.

See the evidence

ItemSourceConfirmation
Appropriation of 42.45 billion dollars · 56 states and territories · up to 2 percent or 849 million dollars for administration · 100/20 Mbps requirementCongressional Research Service R48666 (2025-08-29)2026-08-07
Timeline — 2022-05-13 notice of funding opportunity · 2023-06-30 allocations from 27.1 million to 3.3 billion dollars · 2024-11-19 all initial proposals approved · 2024-12-23 full obligation · 2025-01-16 three final proposals approvedCongressional Research Service R48666 (2025-08-29)2026-08-07
2025-06-06 Restructuring Policy Notice — rescinded all prior final proposal approvals, removed seven non-statutory requirements, 90 days to resubmit, Benefit of the Bargain Round requiredCongressional Research Service R48666 (2025-08-29)2026-08-07
As of August 2025 no deployment project had been funded from allocated BEAD money · statutory four years from subgrant to serviceCongressional Research Service R48666 (2025-08-29)2026-08-07
Benefit of the Bargain Round deadline 2025-09-04 · about 13 billion dollars then reserved for non-deployment · cost per location 2,080 dollars in Maine to 13,420 dollars in HawaiiInformation Technology and Innovation Foundation (2025-09-09)2026-08-07
26 of 56 final proposals approved by 2025-12-02 · about 21 billion dollars under budget · 66 percent fiber, 21 percent low earth orbit satellite, 11 percent fixed wireless · Ohio up 13 percent, Indiana down 7 percentBroadband Breakfast (2025-12-02)2026-08-07
GAO opinion of 2025-12-16 · Louisiana 1.36 billion dollar allocation to a 498 million dollar deployment budget for roughly 124,000 locations · Delaware 13.4 million dollars for roughly 4,700 locations · Nevada full coverage at lower costJD Supra legal analysis (2025-12-26)2026-08-07
GAO finding reported as a violation of the Congressional Review Act · NTIA missed its own target of approving every state by the end of 2025 · first approval batch in NovemberGovernment Executive (2026-01-05)2026-08-07
50 of 56 final proposals approved as of 2026-02-09 · about 21 billion dollars in savings · 2026-02-11 listening session with more than 1,000 unique participantsBenton Institute for Broadband and Society (2026-02)2026-08-07
3,379,711 locations without 100/20 Mbps service · 2,278,355 funded by BEAD · 1,101,356 unfunded · 1,342,667 unfunded units · 33.7 percent of BEAD locations already have terrestrial 100/20 serviceBroadband Expanded analysis of final proposal data (2026-02-09)2026-08-07
Counts of final proposals approved, NIST reviews cleared and award agreements signed as of 2026-08NTIA BEAD Progress DashboardURL not confirmed: every fetch of the NTIA hosts failed TLS certificate verification in this round

The Congressional Research Service report was read directly as a PDF, and it is the source of every pre-2025-09 date and dollar figure above. Nothing published by NTIA was read at first hand — the NTIA hosts could not be opened, so the agency statements above reach this dossier through the CRS report and the trade press that quote them. The underspend figure of roughly 21 billion dollars was confirmed twice from independently opened documents dated 2025-12-02 and 2026-02-09. One commercial funding tracker was opened and then discarded: it stated that 39 states remained in the challenge process, which contradicts the approval counts in every other source here, and none of its figures were used.

This table holds 11 evidence rows, 10 of which carry a source you can open · 7 distinct sources. How this table is made

People affected

Estimated range 2,278,3553,379,711 As of 2026-02

Derivation chain

TermValueSourceAssumption
Broadband serviceable locations in the United States without 100/20 Mbps service3,379,711A commercial data provider's analysis of approved BEAD final proposal data, 2026-02-09Upper bound. Every location the program set out to reach that still lacks service, whether or not an approved final proposal funds it
Locations funded by approved BEAD final proposals2,278,355Same analysis, 2026-02-09Lower bound. These locations hold a funded commitment on paper and have no confirmed service; they are what the 42.45 billion dollar appropriation has promised and not yet delivered
Locations left unfunded after BEAD awards1,101,356Derived: 3379711 minus 2278355. Not used as a bound. It is the part of the gap that the program does not close even on paper, and it is the difference between the two bounds above

Sensitivity The interval is not a confidence interval. It is the distance between two definitional boundaries measured in the same document on the same date: what BEAD promised and has not built (2,278,355) against everyone still without service (3,379,711). The unit is broadband serviceable locations, not persons. No household or occupancy figure was confirmed in this round, so the conversion to people was not attempted, and the number of people affected is larger than the upper bound. The same source reports 1,342,667 unfunded units against 1,101,356 unfunded locations, so a unit count runs about 22 percent above a location count and the funded slice presumably carries a similar ratio. A correction runs the other way as well: the source reports that 33.7 percent of BEAD locations already have terrestrial service at 100/20 Mbps, which means the BEAD eligible list and the list of locations actually without service are not the same set. Neither adjustment was applied because the source does not give the cross-tabulation needed to apply it.

Regional breakdown No document opened in this round gives state level location counts and the national total together. The Louisiana figure of roughly 124,000 locations and the Delaware figure of roughly 4,700 locations come from a legal trade analysis, while the national totals come from a separate analysis of final proposal data, so summing them against the national figure would be mixing bases. Splitting the national count by state population would be proportional allocation, and the distribution of locations without broadband does not follow population.

What is missing 2

Grouped by how it gets filled, not by block number — that axis is the only one that tells a reader what can be done next.

1Fills with researchThe material exists. We simply have not looked yet.
  • Section
    What is it connected to?

    plausible links run to the high cost programs of the Universal Service Fund, to the end of the Affordable Connectivity Program, to rural depopulation, and to the federal permitting timeline that the 2025-06-06 notice also addressed. Relation type and evidence grade were not researched in this round.

    Fills with research
1Needs a new measurementNo published source carries this value. Someone has to count it.
  • Section
    What is the state now, and what should it be?

    no national completion date and no numeric coverage target appears in any source opened for this dossier. The only dated obligation confirmed is per subgrantee and statutory: a subgrantee must deploy the network and begin providing service to customers no later than four years after receiving the subgrant, and the state may extend that deadline under certain circumstances. That clock starts at the subgrant, which is the very step the program spent four years reaching.

    Needs a new measurement

Voting and commenting require you to be signed in. Sign in from the account page

Comments

Total comments
0

The comment was empty, so nothing was posted.

The comment exceeded the limit, so nothing was posted. We do not truncate and save.

You just posted a comment. Please try again in a moment.

The target comment could not be found, so nothing was posted.

You must be signed in to comment.

You have already reported this comment. Each person counts once — to withdraw it, use Cancel report under Reports you filed on the notifications page.

This report has already been reviewed. A judged report cannot be filed again or withdrawn.

No reason was chosen, or Other was picked without a note, so the report was not filed.

You cannot report your own comment or your own profile. Use Delete to take down your own comment.

Report received. Once 3 different people report it, the comment is hidden until review finishes — the outcome appears on your notifications page.

Voting and commenting require you to be signed in. Sign in from the account page

No comments yet.